Thailand LUANGPHAENG Substation EPC Project Successfully Completed the First Piling and Testing Works

Apr 09,2018

On April 7th, 2018, the Piling works for Thailand LUANGPHAENG Substation EPC Project, tendered by NARI Group Corporation, officially commenced construction, and the first piling and testing works has been successfully completed, which marks the new stage of the project. The pile of the project includes 233 sets of spun process, which is expected to be completed in May, 2018.

Thailand LUANGPHAENG Substation EPC Project was signed on November 23rd, 2017 as a turnkey project, with working scope includes design, civil construction, equipment procurement, delivery, installation, testing and commissioning. The owner is Metropolitan Electricity Authority (MEA), with a construction period of 510 days. It is planned to be put it into operation on April 17th, 2019.